The Times Journal & Russell County News
Friday, Apr. 25, 2014 — RUSSELL SPRINGS & JAMESTOWN, KENTUCKY — russellcounty.net
Get online news updates FREE - Subscribe:  [?]
Google

Dam fix requires more time, funding
In Jan. 27 Issue

Delays caused by drilling problems in a critical area near the concrete portion of Wolf Creek Dam are expected to push completion of the project and the money to fund it beyond the previously announced figures and date of December 2012, according to the Corps of Engineers.

No final date for completion on the project has been announced.

The foundation remediation contract for the multi-million dollar rehabilitation is approximately 44 percent complete as of now. Recent instrumentation data and observations from the Corps have shown no abnormalities in terms of stability of the dam. This data is monitored 24 hours per day, seven days per week.

Last week the Corps gave their first project update since Nov. 1 of last year, saying that despite the recent cold and snowy weather work has continued on the giant structure as normal.

Treviicos Soletanche JV, the dam's construction firm, is continuing grouting in Critical Area I, the most questionable area beneath the structure where the most seepage has occurred, and is currently installing the protective concrete embankment wall and the pile barrier wall. They are also in the initial stages of gallery and plaza grouting, according to the Corps.

The Corps awarded the main foundation and plaza grouting contract to The Judy Company at a price of $6.8 million. The preconstruction conference was Jan. 20, at which time notice to proceed on the project was given. The expected contract completion date for that portion of work is May 2012.

The Corps said in their update that 289 protective concrete embankment wall (PCEW) panels and 186 secant piles have been inserted in the large earthen portion of the dam. The PCEW panels are designed to fortify a stabilizing wall in the earthen part of the dam ahead of drilling for the secant piles that will form the permanent concrete barrier wall.

Other construction activities currently in the works include directional drilling, pre-drilling, pile drilling, concrete placement and verification coring.

When the remedial work is complete, the earthen portion of Wolf Creek Dam will be packed with three concrete walls, according to the Corps. These include the diaphragm completed in 1979, the protective concrete embankment wall and the permanent barrier wall.

The Corps and Treviicos Soletanche JV are in the proposal and negotiation stage of a modification to the contract to install cased secant piles in the cave and core trench area of Critical Area 1. Negative impacts to project cost and completion schedule are expected, which means the figure will likely be above the estimated $584 million to complete the project and how much longer beyond December 2012 it will take to complete work on the structure.

The final impacts will be released upon completion of the contract negotiations.

Subcontractor Hayward Baker Inc. continues their drilling and grouting of the rock foundation below the cave and core trench features in Critical Area 1.

All work in that area was suspended in March last year after an increase in movements in the range of one inch or less was observed primarily in monitored cracks along the crest of the dam, according to the Corps.

The initial concern was these movements might be caused by a deep slope movement in the upstream embankment. Work resumed on Critical Area I in the fall with a new method that differs from the original in that the overlapping concrete piles that form the barrier will be installed through temporary steel casing advanced ahead of the excavation.

This move isolates the cave and cutoff trench material outside the casing from the effects of the construction activities inside the casings, according to Michael Zoccola, chief of civil design for the Nashville District.

Zoccola said this approach was slower but that it satisfied concerns regarding dam safety and constructability.

Hayward Baker Inc. has completed a line of holes to close area between the ends of the upstream and downstream grout lines and are currently drilling steep angled holes at the west end of the work platform to tie in with the grout lines drilled from the gallery beneath the concrete dam in 2007.

Currently there are no plans to raise the pool level elevation above 680 ft. above sea level until the main barrier wall is completed, which means the lower lake level will be here for a while longer.

Content Management Powered by CuteNews
SUBSCRIBE to The Times Journal: CLICK HERE

SPONSORED LINKS


Publish Yourself PUBLISH YOURSELF
You can publish news about your group or organization directly to our site, using your computer.
CLICK HERE
Laker Band LAKER BAND
Visit the award-winning official web site for the Russell County Marching Band.
CLICK HERE
Lake Cumberland Web Cams LIVE WEB CAMS
Views of Lake Cumberland as it is right now, from a number of web cams.
CLICK HERE
Lake Cumberland LAKE CUMBERLAND
lakecumberland.com
Official site for Lake Cumberland with everything for the lake visitor and fisherman.
CLICK HERE
The Times Journal is a weekly newspaper issued on Thursdays. It was first published on October 13, 1949, by Andrew J. and Terry Norfleet.
-
P.O. Box 190
120 Wilson St.
Russell Springs KY 42642
Phone: 270-866-3191
Fax: 270-866-3198
Russell County News is a weekly newspaper issued on Saturdays, and is mailed free to every address in Russell County, Ky. It was first published on February 1, 1913.
-
404 Monument Square
Jamestown KY 42629
Phone: 270-343-5700
Publisher:
David Davenport
(publisher@tjrcn.com)
Managing Editor:
Greg Wells
(editor@tjrcn.com)
News & Sports Editor:
Derek Aaron
(sports@tjrcn.com)
Advertising Manager:
Stephanie Smith
(ads@tjrcn.com)
Business Manager:
Kim Haydon
(business@tjrcn.com)
Production Manager:
Renee Daffron
(people@tjrcn.com)
Jamestown Office:
Kim Graham
(rcnoffice@tjrcn.com)
PUBLIC MEETINGS
Members of the public may attend meetings. Boards or agencies may schedule other meetings at special times, but are required to notify the public.
FISCAL COURT: 2nd Monday of month, 6 p.m. in the Courthouse
RUSSELL SPRINGS CITY: 2nd Thursday of month, 6 p.m. in the City Hall Municipal Room
JAMESTOWN CITY: 3rd Thursday of month, 6 p.m. in basement meeting room at City Hall
SCHOOL BOARD: 3rd Monday of month, 6:30 p.m., Board of Education office in Jamestown
LIBRARY BOARD: 2nd Tuesday of month, 5 p.m. at Jamestown Library
AIRPORT BOARD: 1st Tuesday of month, 5 p.m. at Airport
TOURISM COMMISSION: 2nd Wednesday of month, 12:30 p.m. at Tourism Office
CHAMBER OF COMMERCE: 3rd Tuesday of month, noon at The Cove restaurant
LOCAL & AREA
NEWS SITES
The links below open new windows. We are not responsible for the content of the sites.
Laker Country WJRS
(Russell Springs)
lakercountry.com/
WKYM-1017 (Monticello)
wkym.com/
Adair Progress (Columbia)
adairprogress.com/
Casey County News (Liberty)
caseynews.net/
Clinton County News (Albany)
clintonnews.net/
Cumberland County News (Burkesville)
burkesville.com/ccn/
Wayne County Outlook (Monticello)
wcoutlook.com/
Somerset
Commonwealth-Journal
somerset-kentucky.com/
Danville
Advocate-Messenger
amnews.com/
Lexington Herald-Leader
kentucky.com/
Louisville Courier-Journal
courier-journal.com/
WKYT-TV, Lexington
wkyt.com/
WBKO-TV, Bowling Green
wbko.com/
USEFUL SITES
The links below open new windows. We are not responsible for the content of the sites.

RUSSELL CO. OFFICIALS
RUSSELL COUNTY SCHOOLS
RUSSELL CO. LIBRARY

LAKE CUMBERLAND
STATE RESORT PARK
TV LISTINGS:
Choose your service and provider
SOMERSET MOVIE SHOWTIMES

.